Work to lay a new water pipe in the Harlow area will result in some highways disruption. Work has already begun and approximate dates from March onwards are:
Whinney Lane near to the new development and working towards Pannal Ash roundabout commencing 1 March for approximately 9 weeks.
Beckwith Avenue commencing 1 March for 3 weeks.
Harlow Avenue commencing 8 March for 2 weeks.
Beckwith Walk commencing 15 March for 2 weeks.
Beckwith Crescent commencing 22 March for 4 weeks.
Beckwith Road commencing 12 April for 4 weeks.
When working is taking place at Pannal Ash Roundabout a multi-way temporary traffic light system will be in operation 24hrs a day until the work is completed.